TIGHTNESS TEST Settings that define the tightness test modalities of the fuel solenoid valves EN1643 – EN 13577-2 – EN676 – NFPA85 – NFPA86 |
|
|
|
T01 – FILL VALVE OPENING TIME Define the time needed to fill with fuel the test volume. - SKIP TEST (DEFAULT) Must be ≤ 3 seconds according to EN 1643 § 7.101.3 |
|
|
T02 – FILL TEST DURATION The time during which it occurs that the test volume (sealed filled) does not lose pressure due to a leak in the downstream valve(s) depends on the burner capacity, according to the relevant application standard. - 5 … 3600 seconds (default 60) |
|
|
T03 – DISCHARGE VALVE(S) OPENING TIME Define the time required to drain the fuel from the test volume: this is the activation time of the discharge valve(s): - 1 … 25 seconds (DEFAULT 1) |
|
|
T04 – DISCHARGE VALVE(S) The fuel required for the test can be discharged into the combustion chamber or vented into the atmosphere (see relevant standards). Define which valve(s) will be activated during the discharge phase. - VB at terminal F6 (DEFAULT OFF) |
|
|
T05 – EMPTY TEST DURATION The time during which it is verified that the test volume (sealed empty) is not filled with fuel due to a leak in the upstream valve depends on the burner capacity, according to the relevant application standard. - 5 … 3600 seconds (default 60) |